IRS Releases Favorable Ruling On "Placed In Service" Date For A Wind Farm Commissioned But Not Connected To A Transmission Line

The IRS released a private letter ruling on March 15 regarding the placed in service date for a wind farm for purposes of claiming the production tax credit and depreciation.
United States Tax
To print this article, all you need is to be registered or login on Mondaq.com.

The IRS released a private letter ruling (201311003) on March 15 regarding the placed in service date for a wind farm for purposes of claiming the production tax credit and depreciation.   In the ruling, a limited liability company (1) completed physical construction on all wind turn generators (WTG), (2) all of the WTGs will have been individually commissioned and accepted, (3) a final commissioning certificate for the project as a whole was issued, and (4) all the permits and licenses needed to operate will have been issued.  Importantly, the interconnection between the project and the electrical line will not be completed by the end of the year the WTGs will have completed the physical construction, with a temporary arrangement allowing partial generation put in place until the transmission line is completed.  According to the Ruling, the focus in determining a placed in service date is on ascertaining from the relevant facts and circumstances the date the unit begins supplying product in such a manner that it is routinely available and is consistent with the unit's design.  The Ruling concludes that the project will be considered placed in service even though the transmission line is not yet connected to the project and the temporary output is below full capacity.  This is significant for companies trying to qualify for the renewable energy projects that require a placed in service date to qualify for the credit or qualify for bonus deprecation in certain years where the project had not been completed.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

IRS Releases Favorable Ruling On "Placed In Service" Date For A Wind Farm Commissioned But Not Connected To A Transmission Line

United States Tax

Contributor

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More