ARTICLE
27 October 2012

Epc Contracts In The Renewable Energy Sector - South African Re Ipp Programme - Lessons Learned From Phases 1 And 2 (October 2012) Part 1

EPC contracts are the most common form of contract used to undertake construction works.
Australia Real Estate and Construction
To print this article, all you need is to be registered or login on Mondaq.com.

INTRODUCTION

Engineering, Procurement and Construction ("EPC") Contracts are the most common form of contract used to undertake construction works by the private sector on large scale and complex infrastructure projects 1 . Under an EPC Contract, a contractor is obliged to deliver a complete Facility to a developer who need only 'turn a key' to start operating the Facility; hence EPC Contracts are sometimes called turnkey construction contracts. In addition to delivering a complete Facility, the contractor must deliver that Facility for a guaranteed price by a guaranteed date and it must perform to the guaranteed level. Failure to comply with any requirements will usually result in the contractor incurring monetary liabilities.

Due to the flexibility, the value and the certainty derived to sponsors and lenders, EPC Contracts are being used as the main form of construction contract by project sponsors bidding for projects under South Africa's Renewable Energy Independent Power Producer ("RE IPP") Procurement Programme.

This paper is set out in two parts. Part 1 outlines the current context of renewable energy policy and legislation in South Africa, the basic features of the renewable energy technologies, lessons learned from the lenders' bankability requirements and other key issues arising in relation to EPC Contracts in the context of the RE IPP Programme. Part 2 sets out the key features of EPC Contracts in the context of renewable energy projects more broadly.

PART 1 - RENEWABLE ENERGY IN SOUTH AFRICA AND THE RE IPP PROGRAMME

Policy context

On 17 March 2011, the South African Government approved the Integrated Resource Plan 2010 ("IRP") for electricity. The IRP outlines the Government's plan to increase South Africa's total installed electricity capacity from 260 TWh in 2010 to 454 TWh in 2030, an increase of more than 170% over the 20 years. Of this amount, 42% of the new installed capacity is planned to be sourced from renewable energy. The Government's key policy mechanism for achieving the targeted amount of installed capacity of renewable energy is the RE IPP Programme.

RE IPP Programme - overview

Under the RE IPP Programme, Bidders submit Bid responses to construct and operate renewable energy projects and sell power to Eskom.

The renewable energy technologies comprising the RE IPP Programme, and their envisaged split, are set out below:

Technology Proposed amount Percentage allocation
Onshore wind 1850MW 49.7%
Concentrated Solar Power 200MW 5.3%
Solar Photovoltaic 1450MW 38.9%
Biomass 12,5MW 0.3%
Biogas 12,5MW 0.3%
Landfill gas 25MW 0.7%
Small hydro (<10MW) 75MW 2%
Small Projects IPP (max MAW) Total threshold of 100MW 2.8%
Total 3725MW

Each of the renewable energy technologies comprising the RE IPP Programme have a set minimum capacity and maximum installed capacity.

The RE IPP Programme is comprised of five phases, pending subscription by Bidders of the total allocation of MW for each technology. All allocations for each form of technology are made available during the each Bid submission phase. Where an allocation is undersubscribed, the remaining MW will be made available to Bidders in the following phase.

The First Bid Submission Date was 4 November 2011 and the first selection of 28 Preferred Bidders was announced at COP 17 in Durban on 7 December 2011. Preferred Bidders were initially required to finalise all of their contractual arrangements by 22 May 2012 and to reach financial close by 19 June 2012. However, the date for financial close has subsequently been extended and remains outstanding, with Preferred Bidders requested to extend their Bid validity period until the end of October 2012.

The Second Bid Submission Date was 5 March 2012, and 19 Preferred Bidders were announced on 21 May 2012. Preferred Bidders were initially required to reach financial close by December 2012, but this date has been extended to 18 - 28 March 2013. The Third Bid Submission Date has also been extended from 1 October 2012 to 7 May 2013.

RE IPP Programme - proposed update

It has been recently reported that the DOE is proposing to procure an additional 3200 MW of renewable energy capacity by 2020, over and above the 3725 MW being procured currently under the RE IPP Programme.

On 9 October 2012, Engineering News reported:

Addressing a South Africa-Spain Business Summit in Johannesburg, Department of Energy (DoE) acting chief director Thabang Audat said the proposal had been sent to the National Energy Regulator of South Africa (Nersa) for its concurrence on the additional allocation.

He was unable to provide details as to how the new allocation would be divided between the various renewables technologies, but said this breakdown would be provided in a Ministerial determination, which would be published in Government Gazette within seven working days of Nersa's concurrence.

The new renewables allocation meant that there would now be more than 4 360 MW of capacity available for future bidding rounds, with the next round scheduled to close in May, 2013.

Prior to this extension only 1 165.6 MW of capacity remained unallocated under the REIPPP, following two bidding rounds during which a total of 47 projects were named as preferred bidders.

Technologies utilised under the RE IPP Programme

Wind Farm Projects

A wind farm typically comprises a series of wind turbines, a substation, cabling (to connect the wind turbines and substation to the electricity grid), wind monitoring equipment and temporary and permanent access tracks. The wind turbines used in commercial wind farms are generally large slowly rotating, 3 bladed machines that typically produce between 1.5 MW and 3 MW of output. Each wind turbine is comprised of a rotor, nacelle, tower and footings. The height of a tower varies with the size of the generator but can be as high as 100m. The number of turbines depends on the location of the wind farm and capacity of the turbines.

The amount of power a wind generator can produce is dependent on wind availability and speed. The term "capacity factor" is used to describe the actual output of a wind energy Facility as the percentage of time it would be operating at maximum power output.

Wind farms need to be located on sites that have strong, steady winds throughout the year, good road access and proximity to the electricity grid.

Solar Projects

Solar energy projects can be divided into two broad categories, solar photovoltaic ("PV") and concentrated solar power ("CSP").

Solar PV projects utilise power PV cells which are assembled to form solar PV panels or modules that are then lined up in solar arrays. PV cells convert sunlight into electric current using the photoelectric effect. Most solar arrays use an inverter to convert the DC power produced by the solar panels into AC power that can power lights, motors and other loads.

Solar PV plants can use either fixed-mount solar arrays, or automated tracking systems that allow the solar arrays to follow the sun's daily path across the sky to generate more electricity. A solar PV plant typically comprises a series of solar arrays and inverters, a substation, cabling (to connect the solar arrays and substation to the electricity grid), monitoring equipment and temporary and permanent access tracks.

CSP projects use lenses or mirrors and tracking systems to focus a large area of sunlight into a small beam. There are four common concentration technologies, namely:

  • parabolic troughs;
  • dish Sterlings;
  • concentrating linear Fresnel reflectors; and
  • solar power towers.

The concentrated heat provided by the beam is then used to heat a working fluid (commonly molten salt), which is then used for power generation or energy storage.

The amount of power a solar project can produce is dependent on the availability and intensity of sunshine. Most areas in South Africa average more than 2 500 hours of sunshine per year, and average solar-radiation levels range between 4.5 and 6.5kWh/m 2 per day. The annual 24-hour global solar radiation average is approximately 220 W/m 2 for South Africa, compared with approximately 150 W/m 2 for parts of the USA, and approximately 100 W/m 2 for Europe and the United Kingdom. This makes South Africa's solar resources among the best in the world.

Biomass, biogas and landfill gas

Biomass is biological material derived from living organisms, and, in the context of power production, can take the form of forestry residues and wood, agricultural and livestock residues (including straw and animal slurries), sewage wastes, sugar, grains, oils, seeds, and black liquor from paper manufacture.

Energy from biomass is produced through conversion technologies that release energy directly (as heat or electricity), or convert it into another form such as liquid biofuel or biogas. Conversion of biomass may occur through thermal (using heat), chemical, or biochemical processes (using microorganisms). For example, biogas can be produced from an anaerobic digester plant using an air-tight tank containing microorganisms which digest slurry biomass and produce gaseous fuel.

Landfill gas utilisation is the process of processing landfill gas (produced by the degradation of municipal solid waste) into electricity, heat or other fuels. Methane gas produced by landfills must be collected and treated before it can be used for electricity production. Collecting the landfill gas involves extraction through vertical extraction wells or horizontal trenches, from which the gas is then piped to a main collection header before being treated. Treatment of landfill gas occurs via primary and secondary processing systems that remove moisture, particulates and other constituents. Landfill gas can be used for electricity production using an internal combustion engine, gas turbine, microturbine or fuel cell.

Small hydro

Hydro facilities are projects that generate electric power from the movement of water. To generate electricity from water, there must be a dependable flow and sufficient distance over which the water can fall ("head"). In a hydro plant, water feeds from a reservoir through a channel or pipe into a turbine, and the turbine shaft will rotate as pressure from the water builds. The motion of the shaft is converted into electricity via a generator.

A Facility is considered to be 'small hydro' if its generation capacity is relatively low (typically 10MW or less). Small hydro projects may utilise existing dams and abandoned hydro sites. 'Run-of-the-river' hydro projects, whereby a river's flow is diverted through a pipe or tunnel leading to electricity-generating turbines and then returned back to the river downstream, may also be used.

Contractual structure for projects under the RE IPP Programme

An overview of the typical contractual structure for a project financed renewable energy project is set out in Part 2. The outline below relates specifically to the contractual structure used under the RE IPP Programme.

Under the RE IPP Programme, Bidders are also required to submit as part of their Bid the detailed heads of terms of the contracts that they would enter into with their contractors, equipment suppliers and other subcontractors if selected as a Preferred Bidder. In most cases this will be comprised of a detailed heads of terms for an EPC Contract and an Operating and Maintenance ("O&M") Contract.

If a Bidder is selected as a Preferred Bidder, it will negotiate and prepare fully termed EPC and O&M Contracts based on the detailed heads of terms submitted as part of their Bid.

Preferred Bidders will be required to enter, as project company, into the following non-negotiable agreements with the relevant counterparties in order to reach financial close and develop the Facility:

  • Power Purchase Agreement ("PPA") with Eskom;
  • Implementation Agreement ("IA") with the Department of Energy ("DoE");
  • Transmission Agreement or Distribution Agreement (as relevant, depending on which network the Facility will connect to); and
  • Direct Agreement,

(together "the Project Documents").

Key issues and 'lessons learned' under the RE IPP Programme to date

Overview

We have set out below some of the key requirements that Preferred Bidders will be required to meet as the project company under the Project Documents, including our experience of the lenders' bankability requirements from Phase 1 and Phase 2 of the RE IPP Programme, and consider the effect of these requirements and how they may be flowed through to the relevant contractors. The terms "Buyer" and "Seller" are used below in relation to obligations set out in the Project Documents, referring to Eskom and the project company respectively. The capitalised terms used in this section relate to defined terms from the Project Documents.

Overriding pass-through of obligations from the Project Documents

To limit gaps in liability and minimise the need for additional sponsor support, project companies will seek to ensure that the EPC Contracts used in respect of RE IPP Programme projects are bankable, in particular the obligations, risks and liabilities under the PPA and other Project Documents must be passed through to the contractor to the fullest extent that is possible and commercially feasible. The overriding "pass through" principle is that the contractor must take account of the PPA and other Project Documents in performing the EPC Contract and must not put the project company in breach of those documents. The EPC Contract should provide for an acknowledgement of pass through and assumption of risks by the EPC Contractor. We recommend that the following clause be included:

"The Contractor has reviewed the terms of the Power Purchase Agreement, Implementation Agreement, [Distribution Agreement or Transmission Agreement] and Direct Agreement (Project Documents) and, subject to specific limitations agreed in this Contract; assumes those risks relevant to the Works which are assumed by the Owner under the Project Documents; will perform its obligations under the Contract in such manner as to allow the Owner to comply with its obligations under the Project Documents regarding completion of the Facility; and must not do anything to prevent or interfere with the Owner's performance of its corresponding obligations under the Project Documents."

There are three categories of obligations, risks and liabilities that should be passed through to the contractor:

  • explicit obligations;
  • risks or potential liabilities, but no specific obligations; and
  • requirements to take certain action to allow the project and the project company to comply with the requirements of the Project Documents.

If a particular risk cannot be passed through to the contractor, the risk will need to be mitigated by some other means, such as through insurance and/or by the provision of some additional form of sponsor support.

'Pass through' and linked entitlements

Where any entitlements of the contractor arise as a result of the project company being entitled to relief under the Project Documents, including in relation to events of Force Majeure, as well as for Compensation Events, System Events or Unforeseeable Conduct, to avoid gaps in liability under the Project Documents and the need to provide additional sponsor support, the contractor's entitlement under the EPC Contract should be linked to, and limited by, reference to what the project company (as the Seller) receives under the Project Documents, rather than what the project company is or may be entitled to. We recommend that the following clause be included, subject to the project company being required to comply with the process for claiming relief under the Project Documents:

"the Contractor agrees to accept in full and final satisfaction of any Pass Through Claim, the amount agreed or determined as payable under the Project Documents."

Force Majeure

The definition of 'Force Majeure' under the PPA is an exclusive and relatively restrictive definition. For further discussion about force majeure clauses generally, please refer to the force majeure section in this paper below.

To minimise the risk of the project company being required to grant an extension of time to the contractor when the project company is not able to obtain relief under the PPA, the definition of force majeure in the EPC Contract should be back to back with the definition in the PPA.

In addition, given that the PPA does not provide a right to terminate for an extended force majeure, lenders will generally require that no such right to terminate is provided in the EPC Contract or, if such right is provided, that additional sponsor support is also provided.

If an event of Force Majeure occurs prior to the Scheduled COD, the PPA allows for an extension of time by postponing the Scheduled COD for 'such time as shall be reasonable for such a Force Majeure event, taking into account the likely effect of the delay' (clause 16.5).

The Seller will also be entitled to relief if, during any 12 month period, the cumulative duration of Force Majeure events or their consequences (each of which event must last 24 hours or longer) exceeds 60 or more days and the Seller is not entitled to bring a claim under any insurance policy is required to hold under the PPA in respect of those Force Majeure events. In such circumstances, clause 16.9 of the PPA provides the Seller with an entitlement to an extension of the Term and/or other relief from the Buyer to 'place the Seller in the same overall economic position as it would have been in but for such Force Majeure event', provided that any compensation must not be in monetary form and the total extension of the Term must not exceed ten years.

To avoid any gaps in liability arising, the project company should ensure as far as possible that the relief available under the EPC Contract for a Force Majeure event is back to back with the provisions of the PPA.

We recognise that this may be difficult to achieve in practice given the relatively narrow definition of Force Majeure in the PPA and the Self Build Agreement (to be discussed later in this paper).

Compensation Event

The definition of 'Compensation Event' under the PPA includes material breaches by the Buyer of obligations under the PPA, including failure to make payments at the relevant time.

Under clause 15.3 of the PPA, the Seller will be entitled to both an extension of time and additional costs (either additional cost incurred by the Seller before the Commercial Operation Date or capital expenditure at any time) for a Compensation Event. Relief under the EPC Contract for a Compensation Event should be back to back with this.

Under clause 15.3.2 of the PPA, the Buyer has the option to make payments for additional costs in respect of a Compensation Event in either a lump sum or by instalments. If the Buyer chooses to pay the amount in instalments, lenders will need to consider how the increased costs during construction or the additional capital costs after the Commercial Operation Date will be financed. To address this issue, we recommend that the following clause be included:

"Subject to the Contractor complying with the notice and other requirements under this Contract, to the extent that the Owner is entitled to claim relief under the Project Documents for any System Event, Compensation Event, Force Majeure and Unforeseeable Conduct, the Contractor is entitled to claim corresponding relief under the Contract mutatis mutandis, irrespective of whether or not the Owner actually claims such relief under the Project Documents, provided that where a payment must be made by the Owner to the Contractor similar to the payment contemplated in clause 15.3.2 or 17.6 of the PPA, the Owner will make payment in the manner contemplated in clause 15.3.2.2.1 or 17.6.1 of the PPA (as the case may be), and not in the manner contemplated in clause 15.3.2.2.2 or 17.6.2 of the PPA (as the case may be). Accordingly, the Owner will not be relieved from its obligations due to its failure to comply with the notice and other requirements under the Project Documents, or its failure to claim relief under the Project Documents."

System Event

Under clause 14.1 of the PPA, the Seller will be entitled to relief for a 'System Event', defined as delays in connecting the Facility to the grid and the unavailability of the grid. The definition of 'System Event' specifically excludes circumstances 'caused by any natural force or event'. However, the PPA does not provide any definition of the term 'natural force or event'. In addition, under clause 14.1 of the PPA, the Seller is not entitled to bring a claim in relation to a System Event unless the time that the System Event(s) have endured is greater than the Allowed Grid Unavailability Period for a Contract Year or the period that the Commercial Operation Date is delayed beyond the Scheduled COD.

© DLA Piper

This publication is intended as a general overview and discussion of the subjects dealt with. It is not intended to be, and should not used as, a substitute for taking legal advice in any specific situation. DLA Piper Australia will accept no responsibility for any actions taken or not taken on the basis of this publication.

Given that the duration of the 'Allowed Grid Unavailability Period' is not insignificant, representing 2% of the total hours available in a year, this may be a material issue and may not be able to be fully passed through to the contractor. If the contractor will not accept a full pass through of risks relating to the Allowed Grid Unavailability Period and the exemption for a 'natural force or event', the project company may be required to provide some form of sponsor support.

Under clause 14.1 of the PPA, the Seller will be entitled to both postponement of the Last COD and/or a Deemed Energy Payment for a System Event. 'Deemed Energy Payments' are defined under the PPA as an amount payable by the Buyer to the Seller in respect of Energy Output that would otherwise be available to the Buyer, but for a System Event or a Compensation Event, calculated in accordance with Schedule 6 of the PPA with reference to the Commercial Energy Rate and dependant on the period in respect of which such payment is due and payable.

The method by which the amount of the Deemed Energy Payment is determined is set out in Schedule 6 of the PPA. To the extent that this amount will not cover the contractor's delay costs during a System Event, this will become a risk to the project company which would require appropriate sponsor support.

DLA Piper Australia is part of DLA Piper, a global law firm, operating through various separate and distinct legal entities. For further information, please refer to www.dlapiper.com

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More