The protester alleged that GSA failed to conduct meaningful discussions by not raising, in pre-corrective action discussions, significant weaknesses that resulted in the proposal being rated unacceptable...
United States Food, Drugs, Healthcare, Life Sciences
To print this article, all you need is to be registered or login on Mondaq.com.

Life Science Logistics, LLC

B-421018.2, .3

  • The protester alleged that GSA failed to conduct meaningful discussions by not raising, in pre-corrective action discussions, significant weaknesses that resulted in the proposal being rated unacceptable in a post-corrective action evaluation.
  • GAO has held that, when an agency seeks revised proposals and performs a new evaluation, that reevaluation may identify flaws in a materially unchanged proposal that the agency would have been required to discuss with the offeror, had the flaws been identified when the proposal was initially evaluated.
  • In that situation, the agency must reopen discussions in order to disclose its concerns.
  • GSA argued Life Science's pre- and post-corrective action proposals were materially different, but GAO found that the content that gave rise to the significant weaknesses was present in both proposals but had been overlooked in the initial evaluation.
  • Since the Agency did not advise Life Science of the significant weaknesses in its initial proposal when conducting discussions, GAO sustained the protest and recommended GSA reopen the procurement, conduct meaningful discussions, and evaluate revised proposals.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

60-Second Sustains: Life Science Logistics, LLC

United States Food, Drugs, Healthcare, Life Sciences
Contributor
See More Popular Content From

Mondaq uses cookies on this website. By using our website you agree to our use of cookies as set out in our Privacy Policy.

Learn More